Proposal Management: Request Action on Award

Overview

The Request Action process is used to request that Office of Research and Sponsored Projects (ORSP) take action on a processing or active Award. Request Action can be completed from the Award (AWD) workspace by Principal Investigators (PIs), Sponsor PIs, Primary Post-Award Contacts, Administrative Personnel, and Approvers in the Administrative Home roll-up. The request will go to the PI and departments with automated routing for signatures.

The Award Change Request (ACR) record will have its own ID number appended to the Parent Award ID (e.g., AWD000000-ACR000). ORSP will review the ACR and determine if a modification is required. If an Award Modification (MOD) is created by ORSP, it will also have its own ID number (AWD000000-MOD000). Modification data is updated to the Award once the MOD is Active. See Award Modifications for more details.

This procedure has the following sections:

Navigation

Role: PI & Project Team > Home workspace > Award | In Progress | or Active tab > Award workspace

Step-by-Step Process

How to Create an Award Change Request

  1. Click the Request Action button on the AWD workspace.
  2. Select the Request Types. More than one type can be selected (except for "Other Action").
    • An "Other Action" Request Type is to request ORSP action (e.g., process, sign, submit documents; update Award record with a HUM, PRO, or IBCA ID).
      Note Other Action requests route directly to ORSP and cannot be selected in combination with any other ACR type.

screenshot of Award Change Request form steps 2-3

  1. Click Continue
    Notes
  • Notice that an ACR ID number has been appended to the Award ID.
  • Your answer selections determine which pages and questions subsequently display.
    • This procedure shows "No Cost Extension" as an example.
  1. Review the instructions at the top of the page.
    screenshot of Award Change Request form steps 4-8
  2. Complete the remaining smartform questions.
  3. Check the box to indicate if information is included in an uploaded document.
  4. Click Add to attach documents. Choose the file to upload, or drag and drop it, then click OK.
  5. Click Continue to complete additional questions.
  6. Review the instructions on the ACR Final Page.
    screenshot of Award Change Request form steps 9-14
  7. Select Yes/No to Is there a sponsor deadline for this request?
  8. If Yes was selected, enter the Sponsor's Due Date.
  9. Enter any Instructions to ORSP.
  10. Enter any Project Team Notes for Unit Reviewers/Approvers.
  11. Click Finish.

The Worksheet will close and the Award Change Request workspace opens.
Note The PI and the Primary Post-Award Contact will receive an email notification that an Award Change Request was submitted.

Award Change Request Workspace

The Award Change Request (ACR) workspace displays with a list of various activities that can be performed on the change request.  The list of available activities depends on the State of the ACR and your role(s). From here, you can click the applicable link to:

  • Edit Change Request, if you need to make changes to the request or upload documentation. (View Change Request will display if the ACR is in a non-editable state.) 
  • Print Change Request, if you want to view the change request all on one page or print out the ACR form.
  • Post A Comment, if you need to communicate something else about the change request.
  • Project Team Cancel ACR, if you need to cancel the change request/action (only available prior to routing).
  • Project Team Submit Changes, if reviewers or ORSP requested additional information (only available if returned for changes).
  • Route for Approval, to submit the ACR to the required approvers.
  • See the Parent Award and open the Award workspace.

screenshot of Award Change Request workspace highlighting Activities on the left side

For a complete description, refer to the Award Change Request Workspace

Project Team Cancel ACR

Use the Project Team Cancel ACR activity if an ACR was created by mistake, e.g., when you submitted more than one ACR for the same item, or when the request is no longer needed.
Note This activity is only available prior to routing the request.

  1. Click the Project Team Cancel ACR activity.
  2. Enter Comments, which will be included in the email sent to the Contact PI, Sponsor PI (if applicable), and Primary and Additional Post-Award Contacts.  
  3. Click OK
    The state of the ACR will become "Cancelled".

Submit Changes

If Reviewers or ORSP requested changes and returned an ACR, the Project Team can edit the ACR and resubmit it for review.

  1. Click Edit Change Request.
  2. Enter the additional information needed or changes/updates in the worksheet and click Save
    Note The Change Request worksheet will close and you'll be returned to the ACR workspace. 
  3. Click the Submit Changes activity.
  4. Enter Comments, if desired.
  5. Click OK
    The state of the ACR will move from "Changes Requested" based on the approval requirements.

Route for Approval

Use the Route for Approval or the Route to Post Award Contacts activity if you are ready to send the ACR to reviewers for their approval. See the Route an ACR for Approval step-by-step procedure for details.

The ACR will move to the applicable Review state.

Where to Find ACRs In-Progress

Draft, In-progress, and completed Award Change Requests and Modifications can be viewed in the Award workspace on the Mod/ACR tab.

Once a request is routed for approval, the state will indicate the state of the record, which may include:

  • Unit Review
  • ORSP Review
  • Changes Requested
  • Pending Sponsor Review
  • Complete (used for Requests only)
  • Closed
  • No Action Taken (used for Requests only)
  • Modification Complete (used for MODs only)

screenshot of Award Change Request workspace Mod/ACR tab

Last Updated: 